Yorkshire Brewery Progress Update 3

Progress Update 3 - Basement Excavation

Construction is well on the way down at Yorkshire Brewery in Collingwood. One crane is up, and there is only a small portion of dirt left to be removed. With the major basement demolition, earthworks and piling completed the basement retention walls are almost finished. Preparation for the level 2 basement slab is underway, with the initial drainage works beginning soon. Once completed, the slab for basement level 1 will be poured and services integrated. With the introduction of a second crane within the next few weeks, from there it is out of the ground and up! The Heritage buildings will be the first to begin due to the significant restoration works needed, and then construction on the three main towers will begin.

https://youtu.be/1_RWrFoyUJI

https://vimeo.com/103560526

For more information on this exciting development please contact Nina Mizzi on (03) 9650 3722.

Previous
Previous

Yorkshire Brewery Progress Update 4

Next
Next

Yorkshire Brewery Progress Update 2